Stirling Dr

  • Will experience minor traffic disruptions Monday, January 13th from 7:30 am to 5:30 pm for the repair of a faulty mainline for Rogers Communications
  • Emergency vehicles WILL have access

 

Webber Cres between Rush Pl and 22nd Ave

  • Will be closed Monday, January 13th from 7:30 am to 5:00 pm for a water service repair
  • Emergency vehicles will NOT have access

 

Queensway Blvd crosswalk at end of Patricia Blvd

  • Will be closed Monday, January 13th from 6:30 am to 4:30 pm for a concrete pour
  • Emergency vehicles will NOT have access

 

Freimuller Ave between Neff Cres and Skinner St

  • Will be closed Tuesday, January 14th from 7:30 am to 5:00 pm for a water service repair
  • Emergency vehicles will NOT have access

 

Patricia Blvd Crosswalk at Queensway Blvd and end of Patricia Blvd

  • Will be closed Wednesday, January 15th from 6:30 am to 4:30 pm for a concrete pour
  • Emergency vehicles will NOT have access

 

Foothills Blvd between Chief Lake Rd and North Nechako Rd

  • Will experience traffic disruptions starting Monday, January 27th to Friday, February 7th from 8:00 am until 4:00 pm for utility maintenance on the Telus cable
  • Emergency vehicles WILL have access

 

1215 Lethbridge St

  • Will be closed Wednesday, starting January 3rd until February 9th from 7:00 am to 5:00 pm to facilitate water, storm and sewer tie ins, backfill and paving of road.
  • Detours will be required
  • Emergency vehicles will NOT have access

 

Lethbridge Street from the south end of Lethbridge to the north end of Lethbridge Street

  • Pedestrian traffic and parking will be closed for the construction of the new parkade, from Friday, June 14 2024 to May 2025. Pedestrian re-routing will take place. Traffic will not be affected

 

Quebec Street between 6th Avenue and 7th Avenue

  • 6th Avenue sidewalk between Quebec Street and Dominion Street remains incomplete and closed.